"Suriya" reveals that the Thai-Chinese high-speed train, Phase 2, Korat-Nong Khai, will be entirely overseen by Thailand, using almost 100% domestic materials.

354

"Suriya" reveals that the Thai-Chinese high-speed train, Phase 2, Korat-Nong Khai, Thailand will oversee the entire project itself, using almost 100% domestic materials, confirming international standards, ordering the SRT and SRT to strictly enforce the highest safety standards.

On April 2, 2568, Mr. Suriya Jungrungruangkit, Deputy Prime Minister and Minister of Transport, revealed after the 32nd Joint Committee (JC) meeting for railway cooperation between Thailand and China regarding the Thailand-China high-speed rail project, Phase 2, the Nakhon Ratchasima – Nong Khai section, spanning 356 kilometers, that...

The State Railway of Thailand (SRT) is currently preparing the draft bidding documents (TOR) and is expected to be completed within 2-3 months. The bidding process will then begin and construction will begin in 2568. When the project is completed, it will link high-speed rail transport between Bangkok, Laos and China.

In line with the strategy for developing infrastructure to connect regions, for the second phase of the bidding, international bidding will not be used. Thai contractors will be used, confirming that it complies with the conditions of the Government Procurement and Supplies Management Act 2.

Mr. Suriya continued that the Thai side will oversee the construction of the second phase of the high-speed rail project itself, including designing and inspecting the designs itself, and will use almost 2 percent domestic materials, with intensive inspections of the entire system.

However, he believes in the capability of Thai engineers, which is in line with international standards and is acceptable to the Chinese side. In addition, he has ordered the SRT and the Department of Rail Transport (DRT) to strictly monitor the construction to ensure that it complies with safety standards.

While the earthquake on March 28, 2568 and the collapse of buildings are important lessons that require a review of the entire construction quality control process, especially large-scale construction projects such as high-speed trains.

The Ministry of Transport has ordered the SRT to inspect the quality of materials and construction of all high-speed rail projects, especially in terms of vibration and earthquake resistance. Lessons learned will be applied to set additional safety standards.

Mr. Veerish Amrapal, Governor of the State Railway of Thailand , stated that the high-speed rail project will require the use of nearly 100 percent domestically produced materials, particularly regarding the testing of construction materials. Quality assurance will be required at every stage, from production sources to equipment installation. This includes factory inspections for production approval and certification, and the steel from factories must undergo quality testing according to specifications before being used.

There will be additional testing from the Thai standard, which is that each size of steel must be fatigue tested. At the same time, when the steel arrives at the construction project, the steel tag must be collected for inspection, and random sampling by the supervisor and testing must be performed according to the specifications.

Before pouring concrete, the supervisor will randomly check the quantity and size of the steel. Once it passes the standard, the concrete will be poured.

Regarding the Thailand-China high-speed rail project, Phase 1, covering the Bangkok-Nakhon Ratchasima section of 250.77 kilometers, construction is currently underway and is expected to be completed by 2572. It is confirmed that the project is being carried out to high standards, with all steel structures meeting international standards. Furthermore, it has been reported that the project is using steel from Tata Steel (Thailand) Public Company Limited.

In addition, the construction of the project has already been designed to withstand earthquakes. Meanwhile, the inspection of the contract 3-1 for the Kaeng Khoi-Klang Dong and Pang Asok-Bandai Ma sections, a distance of 30.21 kilometers, with a budget of 9,348 million baht, has the contractor being ITD-CREC Joint Venture No.10 Co., Ltd., which is currently working with the Steel Institute and engineers with expertise to conduct the inspection. The results are expected within 2 days.

 

Read all economic news throughout Thailand here.